Crew Man-Hour Calculator

Turn a quantity and a per-person production rate into crew hours and total man-hours. Use it for labor planning, not as a substitute for a bid schedule.

Same unit as the production rate

Units per hour per person

Number of people on the operation

Enter your values, then press Calculate.

How to calculate

Enter the work quantity in the same units as the production rate (for example CY and CY/hour/person, or LF and LF/hour/person). Enter how many people are on the crew. The result is wall-clock hours and total man-hours.

Formula

Crew production = rate per person × crew size. Hours = quantity ÷ crew production. Man-hours = hours × crew size, which also equals quantity ÷ rate per person.

Common use cases

  • Trenching labor
  • Paving crew hours
  • Checking a production assumption
  • Man-hour budgets

Assumptions

  • Quantity is the remaining work in one consistent unit (cy, lf, sy, …).
  • Rate is per person per hour in that same unit, usually from a similar completed crew.
  • Crew size is headcount on the operation, not the whole company.
  • Man-hours = quantity ÷ per-person rate. Crew hours = man-hours ÷ crew size.

Limitations

  • Does not add weather, mobilization, curing, or access delay.
  • Does not convert a crew rate into a per-person rate. If you only have crew rate, use production rate first or set crew size to 1 and enter crew rate as the person rate only if that is truly what you mean.
  • Does not cost the hours. There is no wage table.
  • Does not split tasks across days except by dividing crew hours by a shift length you apply off-page.

Worked examples

200 units, 5/hr/person, 4 people

200 ÷ 5 = 40 man-hours. 40 ÷ 4 people = 10 crew hours. Same story as 200 cy in 10 hours on the production-rate page, run in reverse.

  1. 1. Crew production

    5 × 4 = 20 units/hr

  2. 2. Hours

    200 ÷ 20 = 10 hr

One person

  1. 1. Crew production

    10 × 1 = 10 units/hr

  2. 2. Hours

    50 ÷ 10 = 5 hr

Hours from a remaining quantity

Use this page when you still have work to do and you already know a per-person rate (from a similar crew or from the production-rate calculator). Hours = quantity ÷ (rate per person × crew size). Man-hours = hours × crew size, which also equals quantity ÷ rate per person. 200 cy at 5 cy/hour/person with 4 people is 10 crew hours and 40 man-hours.

Inverse of production rate

Production rate starts from quantity and hours and reports cy/hour. This page starts from quantity and cy/hour/person and reports hours. Do not mix a crew rate into the per-person field or the hours will be four times too long on a four-person crew. Weather, access, and setup are not included.

Per-person rate is not optional arithmetic

Two hundred cubic yards at 5 cy/hour/person with four people is 40 man-hours and 10 crew hours. If your history is “the crew of four placed 200 cy in 10 hours,” that history is a crew rate of 20 cy/hour, or 5 cy/hour/person — compute it on the production-rate page, then type 5 here. Typing 20 as a per-person rate with four people will understate duration by a factor of four.

Related calculators

FAQ

Does this include weather or mobilization?

No. It is quantity ÷ production only. Add weather, access, and setup on the schedule separately.

What production rate should I use?

Use a measured rate from a similar crew and condition, or a bid-item historical rate. Do not use a catalog rate if the site is tighter or wetter.

What if I only know the crew rate?

Open the production-rate calculator, or divide crew rate by headcount yourself, then enter the per-person rate here. This page expects units per hour per person.

Does crew size include the foreman?

Include whoever is in the rate you calibrated. If the historical 5 cy/hour/person already counted the foreman as a body, keep counting them.

Disclaimer

These calculators are estimating tools for planning and field checks. They are not a substitute for approved plans, specifications, licensed professional engineering, or governing standards. Confirm densities, waste factors, and yields with your supplier and project documents.